SCW expects you to know and follow both industry best practices and all requirements of the applicable AHJ (Authority Having Jurisdiction). This means you will:

  •  Use best practices to route, support, and protect cabling
  •  Leave service loops (minimum 24-inch required)
  •  Label cables
  •  Use the correct cable type for each section of the site (Riser, Plenum, Outdoor/ Direct Burial)