“Hey Jonathan,
I reviewed the Lignetics photos, and these are the issues that I saw:
Camera 4: Exposed cabling, EMB Knockout left open.
Camera 13: Cable pathway is messy above camera location. Needs more support, run diagonally.
Camera 17: Cable pathway is messy. Needs more support, follow the beams.
Camera 20: Did the technician supply that bracket and is it zip-tied to that beam?
Camera 21: Service-loop has the cabling doubled back- bend radius issue possibly.
Camera 22: Cable isn't supported past the service loop.
Camera 23: Cable not supported, zipped to conduit- code violation.
Camera 24: Knockout is open.
Camera 27: Cable not supported. Use the beam to support and hide until camera location.
Cameras 28,29: Knockouts open, cable not supported.
Scrubber Building Switch: Ubiquiti equipment zip-tied to existing conduit. Code violation.
Storage Switch: Cable trunkline needs Velcro, UB equipment zip-tied to existing conduit. Code violation.I hate to say it, but some of these mistakes make me wonder what's going on with the cabling behind these exterior walls that the cameras are mounted on. When the technician returns to tidy these mistakes, can you please have them take some more pictures of cable pathways?
Did the technician throw away those missing knockouts from the electrical mounting boxes? If so, the link I sent for the weatherproof connectors used at New Wave Capital should work for these cameras as well.
Thanks.”
...
Note |
---|
Certificate of Completion sent 5/18/23. |
New Wave Capital
Info |
---|
Install began 1/10/23 |
Hi Calver/Sam,
I'm sending this to both of you as I'm not sure who is the right person for this. The installers "finished" the installation the other night, but I have to admit that I'm a little disappointed. Honestly completely not what I was expecting. Please see attached photo of the wiring that was installed in the hallways of the building. I was always under the impression that the wiring would be covered with some sort of wire mold. We have a similar thing outside which I don't mind as much but its it's just not what I was expecting. Can we get on a call to discuss this on Monday? I don't want to leave the wiring exposed like this. I'm a little disappointed by the camera angles/locations as well. We didn't achieve the overlap in the cameras as we had discussed when putting this together. Example is attached.
...
Note |
---|
COC signed 8/23/23 after multiple remediation trips. No further contact with client. |
Leftridge Transportation
...
Calver-
The camera “C” in the attached wasn’t placed where I originally wanted (and was confirmed in the scope of work) because the tech told me we had a drywall ceiling.
I reminded him we always had a drywall ceiling and wondered why this wasn’t an issue before during the site visit.
Anyway, we agreed on another location – not the view I wanted but good enough.
I will view and sign the completed form shortly.
Thanks,
Note |
---|
COC signed 8/11/23. No further contact with client. |
Riviera Place Apartments/ Scotch Hollow
...
Multiple tech groups and project close-out attempts over 9-month span.
Inaccurate updates by TL Technician relayed to SCW by TL PM’s.
...
Note |
---|
Project still ongoing with countless remediation trips and issued surfaced by client, not Techlink PM’s. |
...
No electrical mounting boxes installed/ damaged mounting surfaces.
Issue noticed by SCW PM, brought to TL PM’s attention.
...
Note |
---|
COC signed 2/26/23- Electrical Mounting Boxes never installed, returned to SCW. |
...
No electrical mounting boxes installed.
Terminations exposed.
Issue noticed by SCW PM, brought to TL PM’s attention.
...
Note |
---|
COC signed 3/2/23 |
Clearway Energy
Info |
---|
Install began 3/21/23. |
Some issues with existing equipment and CO’s, extending the project considerably.
The (2) most recent trips were to install a pair of wireless antennas added to replace an existing pair. Each trip has resulted in damaged antenna pairs, and we believe it’s because the technicians aren’t following directions.
...
Note |
---|
Installation still ongoing- return trip required after third antenna pair shipped to site. |