Make a friendly introduction and explain what is required of you will need from them during the installation:

  • Signing Sign off on the Location Approval Form prior to cameras being mounted,

  • Sign off on the View Approval Form after cameras have been aimed, and the Certificate of Completion when the project has been completed.

  • Working with you and SCW tech support to set up their Remote Viewing Software (SCW Go for mobile devices, SCW ViewStation for PC). It would be helpful to

If possible, have the POC agree on a date/time that they will be available to set up their devices.

  • Sign off on the Certificate of Completion when the project has been completed.

  • Calling into SCW tech support for additional training on the system and software.

...

The Location Approval Form for your specific installation will have been uploaded to the work order as a Required Closeout Document.

This document is designed to ensure that all cameras are mounted where the client wants them. Properly completing this step reduces callbacks or warranty work arising from miscommunication.

Note

Don’t forget to print this the Location Approval Form document prior to arriving on site

...

The signed and completed Location Approval Form must be uploaded to the work order as soon as it as completed. It is a Required Closeout Document . It is and necessary for a completed installation.

Any inaccuracies or changes to the project summary camera locations must be directed to the Techlink project manager. They will notify the SCW Project Manager who will contact the client and process a change order.

...